2024 County Highway Construction and Paving Project Updates as of 11/07/2024
|
A |
CTH JJ East to CTH JJ West Town of Grand Chute |
||
|
Project Description |
This project will improve the existing asphaltic surface by placing an asphalt leveling layer and asphalt overlay for this segment of highway. The paved shoulder will also be widened to current County standards. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards. |
||
|
Project Status |
Milling and paving of the asphalt pavement was completed in mid-October. Crews are scheduled to complete shouldering, guardrail replacement, and final finishing operations in early November. |
||
|
Traffic Impacts |
County A remains open to traffic. Remaining work will be completed utilizing flagging operations and/or shoulder closures. |
||
|
More Information |
|
CB |
WIS 15 to CTH JJ Village of Greenville and Town of Grand Chute |
||
|
Project Description |
Outagamie County conducted an engineering study to evaluate potential alignments for the extension of County CB from WIS 15 to County JJ. The planning, design, construction and maintenance of roadways within the community is a critical component of safe and efficient travel, smart growth planning, and economic development. |
||
|
Project Status |
Recommended alignment was presented to the public in June 2021. Presentations were made to local officials in September 2021. Mapping of the proposed corridor is under consideration by each municipality. |
||
|
Traffic Impacts |
Pending |
||
|
Design Engineer |
Oneida Engineering Services |
||
|
More Information |
|
D |
WIS 76 to CTH XX Town of Deer Creek |
||
|
Project Description |
This project includes a drainage study to determine improvements to the area, design, and ultimate construction of roadway, drainage, and pavement improvements. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards. |
||
|
Project Status |
County crews completed roadway and drainage construction in fall 2023 from the south project limit (WIS 76 intersection) to the Oak Road intersection. This segment was reclaimed and paved in May 2024. Crews completed pavement replacement of the northern portion of the project (Oak Road to CTH XX) in October. Drainage improvements have also been completed. Final finishing and shouldering is currently underway. The surface layer of asphalt pavement is currently scheduled to be placed in 2025 over the entire project. |
||
|
Traffic Impacts |
County D is currently closed to thru traffic with local access maintained. A signed detour has been posted and utilizes WIS 76, USH 45, and Waupaca County D / Outagamie County XX. |
||
|
Design Engineer |
Westwood Infrastructure |
||
|
More Information |
|
F |
Birch Road to CTH M Towns of Deer Creek, Maine |
|
Project Description |
This project will improve the existing asphaltic surface by reclaiming, regrading, and installing a new asphalt pavement for this segment of highway. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards. |
|
Project Status |
Culvert replacement began in early May and asphalt paving was completed in late May. Placement of the surface layer of asphalt is scheduled for 2025. |
|
Traffic Impacts |
Roadway is open to traffic, 2024 work is complete. The surface layer of asphalt is scheduled for 2025. |
|
Design Engineer |
Outagamie County |
|
More Information |
|
G |
Isaar Road to CTH Y Town of Seymour |
||
|
Project Description |
This project is for the design, right-of-way, and future reconstruction of this segment of highway. Associated improvements will include lowering the roadway profile to allow for a wider paved surface and shoulders. Culverts and other roadway appurtenances will also be improved, replaced, or upgraded to current standards. |
||
|
Project Status |
Final design is currently underway. Right-of-way acquisition is currently underway. Construction is scheduled for 2025. A public information meeting was held in late April with materials available on the project website. |
||
|
Traffic Impacts |
County G will be closed to through traffic during construction with local access maintained. A signed detour will be posted and is likely to utilize WIS 55, County VV, and County Y. |
||
|
Design Engineer |
Outagamie County |
||
|
More Information |
|
JJ |
CTH A to WIS 47 Town of Grand Chute |
||
|
Project Description |
This project is for the design, right-of-way and future reconstruction of County JJ to an urban cross section. Current and planned development in the area has prompted the need for reconstruction to improve safety & operational efficiency, improve drainage, and provide multimodal accommodation. This project also includes utility improvements for the Town of Grand Chute and replacement of the existing railroad crossing located east of Wren Drive. |
||
|
Project Status |
Preliminary design continues. Updated project costs and schedules are being prepared for budgeting and planning purposes. |
||
|
Traffic Impacts |
Pending |
||
|
Design Engineer |
Westwood Infrastructure |
||
|
More Information |
|||
|
|
|||
|
JJ |
(OLD STH 15) Givens Road to Greendale Road Village of Hortonville |
||
|
Project Description |
This project will reconstruct portions of the roadway and replace the existing pavement through the Village of Hortonville upon completion of a jurisdictional transfer of former WIS 15. |
||
|
Project Status |
An all-way stop condition was put into effect at the intersections of County JJ (Old WIS 15) & Mill Street and County JJ & Nash Street in late 2023. Preliminary designs were presented to the public in early March and downtown business owners in May in order to confirm the typical cross section. Construction is currently scheduled to begin in 2026. |
||
|
Traffic Impacts |
Pending |
||
|
Design Engineer |
McMahon |
||
|
More Information |
|||
|
|
|
||
|
JJ |
(OLD STH 15) B-44-709 over Black Otter Creek Village of Hortonville |
|
|
|
Project Description |
This project is for the design, right-of-way, and future replacement of the bridge structure to current standards upon completion of a jurisdictional transfer of former WIS 15. |
|
|
|
Project Status |
Preliminary design and hydraulics analysis is complete, including determination of initial right-of-way impacts. Development of the right-of-way plat is underway which will be followed by acquisition. Construction is currently scheduled for 2026. |
|
|
|
Traffic Impacts |
Pending |
|
|
|
Design Engineer |
JT Engineering |
|
|
|
More Information |
|||
|
KK |
B-44-003 Bridge over Kankopot Creek Town of Buchanan |
|
|
|
Project Description |
This project is for the design, right-of-way, and replacement of existing bridge B-44-003 over Kankopot Creek. In addition, approach pavements, culverts, and other roadway appurtenances may also be improved, replaced, or upgraded to current standards. |
|
|
|
Project Status |
Reconstruction of the bridge was completed in late October under a let contract. County crews are currently completing approach reconstruction and placement of the asphalt pavement with guardrail placement and final finishing items to follow. The project is currently anticipated to be complete in mid November. |
|
|
|
Traffic Impacts |
County KK is currently closed to thru traffic with local access maintained. A signed detour has been posted and utilizes WIS 55, County CE, and County GG. |
|
|
|
Design Engineer |
Westbrook Associated Engineers |
|
|
|
More Information |
|||
|
N |
CTH KK to CTH CE Town of Buchanan |
|
|
|
Project Description |
This project is for design, right-of-way, and ultimate reconstruction of this segment of County N. A 3-lane urbanized pavement section is planned as well as expanding the existing Emons/Buchanan Rd roundabout in order to improve capacity and safety. Federal funding has been awarded through the STP-Urban program. |
|
|
|
Project Status |
Right-of-way acquisition and utility coordination are currently ongoing. Utility relocations are currently scheduled to occur throughout 2024 and 2025. Roadway reconstruction has been rescheduled to occur in 2026 (previously 2025). Impacted property owners should expect to receive correspondence in late October that provides an update on the status of right-of-way acquisition and next steps. |
|
|
|
Traffic Impacts |
During future roadway reconstruction, County N will be closed to thru traffic during construction with local access maintained. A signed detour will be posted and is anticipated to utilize County KK, WIS 55, and County CE. There may be additional traffic impacts related to utility relocation prior to the roadway reconstruction in 2026. |
|
|
|
Design Engineer |
Westwood Infrastructure |
|
|
|
More Information |
|||
|
OO |
Richmond Street (STH 47) to 750-ft E. of Meade Street City of Appleton, Town of Grand Chute |
|
|
|
Project Description |
This project will improve the existing concrete pavement by making spot joint repairs and concrete panel replacements for this segment of highway. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards. |
|
|
|
Project Status |
A portion of the project has been awarded for construction. Construction is currently underway between Ballard Road and Meade Street with a few additional spot repairs located between Ballard Road and Conkey Street. |
|
|
|
Traffic Impacts |
County OO is currently closed to traffic between Meade Street and Park Drive Lane. A signed detour is posted and utilizes County E (Ballard Road), I-41, and WIS 47 (Richmond Street). Local access is being maintained between Park Drive Lane and Ballard Road. Thru traffic along County OO is suggested to follow the detour in order to avoid travel delays. |
|
|
|
Design Engineer |
CBS Squared |
|
|
|
More Information |
|||
|
PP |
WIS 54 to WIS 54 Towns of Center, Black Creek |
|
|
|
Project Description |
This project will improve the existing asphaltic surface by placing an asphalt leveling layer and asphalt overlay for this segment of highway. The paved shoulder will also be widened to current County standards. Culverts and other roadway appurtenances may also be improved, replaced, or upgraded to current standards. |
|
|
|
Project Status |
Asphalt resurfacing and major work items have been completed. Final finishing and sign replacements are anticipated to be completed in early November and will complete the project. A portion of the project is currently being utilized as part of a planned detour of WIS 47 under a WisDOT project. |
|
|
|
Traffic Impacts |
County PP remains open to traffic. Remaining work will be completed utilizing flagging operations and/or shoulder closures. |
|
|
|
More Information |
|||
|
U |
County S to County EE Town of Oneida, Brown County |
|
|
|
Project Description |
This project is for the design, right-of-way, and future rehabilitation of this segment of County U. The associated improvements are anticipated to include pavement replacement, spot regrading, drainage and safety improvements, widening the shoulder to current standards, and improving, replacing, or upgrading roadway appurtenances to current standards. |
|
|
|
Project Status |
Preliminary design is complete. A Public Involvement Meeting was held in late May with materials available on the project website. Development of the right-of-way plat is underway. Right-of-way acquisition and final design will follow. Construction is currently scheduled to begin in 2026 and may be completed over multiple seasons. |
|
|
|
Traffic Impacts |
During construction, the project area will be closed to through traffic. A signed detour will be posted, and is likely to utilize County S, County J, County E, and County EE. |
|
|
|
More Information |
|||
|
VV |
Isaar Rd to CTH Y Town of Seymour |
|
|
|
Project Description |
This project will lower the roadway profile to allow for a wider paved surface and shoulders. The roadway will be pulverized, regraded, and a new asphaltic pavement will be placed. Other spot improvements are also anticipated. |
|
|
|
Project Status |
Roadway reconstruction, placement of the lower lift of asphalt pavement, and final restoration was completed in 2023. Crews are currently investigating and addressing areas of unstable base material throughout the project. |
|
|
|
Traffic Impacts |
County VV is currently open to traffic. |
|
|
|
Design Engineer |
Outagamie County |
|
|
|
More Information |
|||
|
Z |
County ZZ to Outagamie Rd Town of Buchanan |
|
|
|
Project Description |
This project is for design, right-of-way, and ultimate reconstruction of County Z to current County highway standards. Federal funding has been awarded through the STP-Rural program for the eastern portion with the western portion being locally funded. Both segments will be combined into a single project for construction. |
|
|
|
Project Status |
Final design and right-of-way acquisition are complete. Utility relocation and adjustment is currently scheduled to begin in fall 2024 and continue until roadway reconstruction in 2025. Roadway reconstruction will occur throughout the 2025 season. |
|
|
|
Traffic Impacts |
County Z will be closed to thru traffic during construction with local access maintained. A signed detour will be posted and is anticipated to utilize WIS 55, County CE, and Brown County D. |
|
|
|
Design Engineer |
raSmith |
|
|
|
More Information |
|||
Future Highway Projects
For future year projects, check out the Highway portion of the Outagamie County Capital Improvement Program.
2024 Outagamie County Project Map
2024-2028 Outagamie County CIP Map
Wisconsin Department of Transportation Projects
For information on state and US highway projects in Outagamie County, contact the Wisconsin Department of Transportation or click on their website pages linked here:
WisDOT Northeast Region Weekly Project Updates
WisDOT Northeast Region Highway Projects and Studies
I-41 Expansion (WIS 96 to CTH F)
I-41 Rehabilitation (Breezewood Lane to WIS 96)
WIS 15 Expansion (US 45 - Lily of the Valley Dr.)
WIS 47 Resurfacing (Village of Black Creek)
WIS 47 & County S Intersection Improvements
WIS 54 Resurfacing (New London to Shiocton)
WIS 54 Improvements (Shiocton to French Rd)
WIS 54 Improvements (French Rd to Seminary Rd)
WIS 76 Reconstruction (Everglade to County JJ)
WIS 76 & School Rd Safety Improvements
WIS 76 (WIS 54 to Waupaca Co. Line)
WIS 96 / Wisconsin Avenue (Casaloma Dr to Badger Ave)
WIS 96 Improvements (Kaukauna to Brown Co. Line)
WIS 96 Resurfacing (Cleary Ct to Tower View Drive)